Project Details
Start Date :
22 March 2017
Completion Date :
30 April 2018
Contract Value :
QR. 110,466,061.36
Client :
Public Works Authority (Ashghal)
Contact Info
  • 6th Floor, Al Mana Plaza, Qatari Bin Fujaah St, Bin Mahmoud . PO Box 7098, Doha Qatar
  • +974 4419 0333
  • +974 4441 8249
  • Info@Petroserv-limited.com

Objective

  • The purpose of this project is to reduce and eliminate flooding at a number of Hot spot locations across Muaither. The solution provided is a combination of standard and novel methods to collect and manage surface water run-off.
  • The proposed network is dual collection system for both Surface and Ground water. The proposal is to connect into the existing network if available or into the deep injection wells with required treatment and attenuation.

Brief description of the works

The general scope of work for design and construction of the Surface Water Drainage system includes, but not limited to:

  • Survey and Design the drainage works
  • Construction of Surface water network
  • Construction of deep injection tank