Top
Project Details
Client:
Qatar Petroleum
Commencement:
January 2007
Completion:
December 2009
Value:
QR 15 M
Duration:
35 Months
Location:
Qatar
Role:
Main Contractor (Design and Build)
Contact Info
  • 6th Floor, Al Mana Plaza, Qatari Bin Fujaah St, Bin Mahmoud . PO Box 7098, Doha Qatar
  • +974 4419 0333
  • +974 4441 8249
  • Info@Petroserv-limited.com
Project Sheet Seals NGL Plant

Description

Works are located at NGL 1, 2 and 3 plants and comprise the design and construction for:

  • Replacement of single mechanical seals with double seals on 54 No. process pumps to improve efficiency.
  • Upgradation of double seals on 22No. process pumps to improve efficiency.
  • Replacement of 4 No. MDEA submerged pumps at NGL, to comply with zero emission requirements.

The works include the following disciplines:

  • FEED Verification.
  • Design and Engineering.
  • Process
  • Mechanical and Piping
  • Instrumentation
  • Remote monitoring and DCS
  • Electrical
  • Civil
  • Structural
  • Loss Prevention
  • Environmental Protection
  • SAP & CMMS